Portal de Cehegin

www.portaldecehegin.com

Cehegin - SpanishCehegin - English
detail of Cehegin

 

The new Holy Bridge passes the load test (27/04/2010)

The Minister of Public Works, José Ballesta, director of Roads, Jose Guijarro, Cehegín mayor, Jose Soria, and council Works and Services and Planning, Chico and Gregorio Juan Antonio Morales, respectively, have been present in the load test of the new Bridge St., last step in his recent inauguration.

Four large trucks, "with more weight than you will at the time the bridge" as Ballesta, have circulated in different parts of the infrastructure, in addition to being stationed at fixed points in order to check the strength of the same .

The result of this test was a complete success, confirming the good performance that has been carried out during the construction of this overpass on the Rio Argos, "that will solve the problems of farmers in the area, access to the hamlet of Canara and Salt Water Industrial Estate, improving driver safety, "said Soria.

With the new Holy Bridge and done, just need to install lighting, soft lighting betting on its parapets, "because this does not remove views of this part of the Casco Antiguo", according to experts.

It has two lanes, large sidewalks and railings, so you can travel by foot.

Furthermore, it has installed vertical and horizontal signaling and marking, so that, according to the mayor, "we will open this bridge in 10 to 12 days."

Source: Ayuntamiento de Cehegín

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información